By the beginning of 2025, the installation of the main equipment at the main berth at Baltic Hub was completed, including the installation of STS rail tracks along its entire length. Almost all fenders and mooring bollards were also installed, work was carried out on the placement of life-saving equipment, navigation lights and metal limiters, which ensured the safety and functionality of the terminal.
The construction of CRMG beams in several areas is ongoing, work is underway on the foundations for containers and steel platforms intended for refrigerated containers. The installation of the rail system is nearing completion: specialists perform welding, drilling, fixing with chemical anchors and priming to ensure reliable fixation.
One of the significant stages was the complete dismantling of the T1 breakwater, freeing up space for new facilities. In addition, the construction of key buildings, including three administrative buildings, fire-fighting tanks and Y3 and Y4 facilities, has been completed, which means the infrastructure is ready for operation.