The next stage of construction of Terminal T3 in Gdansk has been completed.

In September 2024, the next stage of the construction of Terminal T3 was completed, confirmed by the issuance of the Acceptance Certificate. This stage includes the completion of site preparation works for the automated rail-mounted cranes (ARMG), which will play a key role in the operation of the terminal.

The delivery of the first four RMG cranes (out of a planned 20) to Baltic Hub began in late July, and the installation of the equipment began in late September. Four STS (Ship-to-Shore) cranes have also been sent to Gdansk, with the expected delivery date being the end of October 2024. Key installations on the main quay wall have been successfully completed, including protective fenders, pedestrian barriers and navigation lights.

Work is currently ongoing on the installation of a new water supply and drainage system. 14-metre lighting masts are being installed and 5-metre poles are being mounted. Work is also ongoing on the steel bridges for access to the refrigerated containers, and the IT equipment in buildings B1 and B2 is being connected. Construction of the B3 tank for fire safety is also progressing well.

Добавить комментарий